Delivery Update

State: Week 37

General information

The day of release determines the delivery date. | Technical reworking extends the delivery date. | Changes extend the delivery time.


Please note in your planning:
The day of release determines the delivery date. Technical reworking or necessary changes extend the delivery date. Purchased items (e.g. drives) can extend the delivery date. Upcoming public holidays are not production days and extend the delivery time.

15-day delivery programme | commercial doors

The 15-day delivery programme for contract doors is available with the following exceptions:
Doors with glazing, doors with ventilation grilles

15-day delivery programme | sliding doors

15-day delivery programme for sliding doors is currently not available.

 

15-day delivery programme | industrial doors

The 15-day immediate delivery programme for industrial doors is available.

15-day delivery programme | garage doors

The 15-day immediate delivery programme for garage doors is available.
 

STEEL DOORS | Verl

Current delivery time: approx. 5 weeks
with glazing + 2 weeks
with block frame + 2 weeks
Doors ISO+ (dw62) + 2 Weeks
with counter-frame + 2 weeks


Current delivery time special doors: approx. 11 weeks

This applies to elements with the following properties:
hold-open doors, bullet-resistant doors, RC3 with full panic function + RC4 doors, transformer grilles, wicket doors, top panel & fanlight, alarm wire mats, metal butt joint (door width > 1,500mm), soundproof doors (dw 67).

FIRE PROTECTION SLIDING DOORS | Verl

Current delivery time: approx. 8 weeks

INDUSTRIAL DOORS | Verl

Current delivery time: approx. 5 weeks

with wicket door additionally + 1 week
SLW and SL + 1 week

Due to ongoing delivery issues with our drive supplier, there are occasional delays in delivery dates. We are working intensively on a solution and are increasingly relying on alternative suppliers.

GARAGE DOORS | Verl

Current delivery time: approx. 5 weeks

With wicket door: + 2 weeks
Up-and-over doors: + 6 weeks
Doors with special features: + 1 week

*The Golden Oak finish is currently unavailable; the new delivery date has not yet been announced.

STEEL DOORS | Großzöberitz

Current delivery time: approx. 4 weeks

with block frame + 2 weeks
with glazing + 2 weeks
with special colour + 1 week

FOLDING DOORS | Verl

Current delivery time: approx. 8 weeks

ROLLER SHUTTERS | Großzöberitz

Current delivery time: approx.4 weeks

High-speed roller shutters:
ThermoTeck and ThermoTeck "Speed": + 2 weeks

Due to ongoing delivery issues with our drive supplier, there are occasional delays in delivery dates. We are working intensively on a solution and are increasingly relying on alternative suppliers.

HIGH-SPEED FOIL DOOR HSD-I | Verl

Current delivery time: approx. 6 weeks

ASSEMBLY

Current delivery time: approx. 4 weeks

Explanation

 

No restrictions   |  First restrictions  |   Significant restrictions